Location Considerations

The proposed site is located on land to the south of Alehouse Hillock, Cairnie, Huntly, AB54 4UB.

Grid reference: Easting (X) 345804 , Northings (Y) 844836

What3words: ///trek.such.alpha

It is expected that the site will cover approximately 6 acres of land which will include the BESS compound, substation area, landscaping to provide screening to the site and access tracks.

‍ ‍

There are many considerations which must be taken into account when selecting an appropriate site for a BESS. These include but are not limited to:

Requirements of the network: Kedrum BESS has secured and accepted a valid grid connection offer from the Transmission Operator, National Energy System Operator (NESO) / Scottish Hydro Electric Transmission (SHET). The offer follows the necessary technical assessments confirming that the local transmission network can accommodate the proposed 150 MW development. The project has also progressed through the Connections Reform process, demonstrating that it supports an identified network need and has a clear basis for connection. 

Grid connectivity: Locating the development close to the existing transmission network enables a more efficient, technically optimal and commercially viable grid connection. A shorter connection route also minimises disruption and constraints for local communities and the surrounding environment.

Intended application: The siting of a BESS development has important implications for the services it can provide. BESS can provide a broad range of services such as balancing (helping to keep the frequency of the national grid stable), peaking capacity, (increasing the reliance on renewables) and improving network resilience during extreme weather events (keeping the lights on) (NREL, 2019).

Size and topography: The site must be of adequate size with flat or of gentle gradient and free from obstructions which cannot be removed such as streams or historic features.

Environmental constraints: The site must be located away from ‘sensitive sites’ as defined by the Environmental Impact Assessment Regulations (i.e. designated nature conservation sites, word heritage sites or national parks).

Heritage designations: The site must be a suitable distance away from listed buildings, scheduled monuments, and other registered historic designations.

Land Use designations: Consideration is given to a site’s land use planning designation as defined by an adopted Development Plan or an emerging Development Plan. For example, land which is safeguarded for housing or employment would not be suitable for the BESS development and would conflict with planning policy.

Access and Services: The site must have adequate access to facilitate construction and for management and maintenance purposes once the BESS is operational.

Availability: The landowner must be able and willing to accommodate the project for the 40-year project lifetime.

‍ ‍